|
|
|
|
News
• January 04 2004
|
MEPA denies conflict of interest
Three of
MEPA’s employees that made up a group of six to chose the sites
for interim waste landfills will now be involved in vetting the EIA
to decide whether these are the best sites, MaltaToday has learned.
In what as effectively a three-day exercise, MEPA’s acting Director
of Environment, Vince Gauci, waste expert Kevin Mercieca and EIA expert
Rachel Portelli made up half the team that decided the best site lay
300 metres from Mnajda temples.
These same officials are now involved in vetting the EIA reports prepared
by British consultants SLR and Maltese consultants AIS, which should
have performed an audit on the site selection exercise commissioned
by minister Ninu Zammit to choose the best site for the landfills.
Asked by MaltaToday whether there was a conflict of interest, MEPA replied:
"The assessment of the EIS is being handled by the Director General
as Acting Director of the Environment Protection Directorate. Internally
the persons mentioned will be consulted in their technical and professional
capacity. The involvement of these persons is known to the Authority
and MEPA will be taking all precautions."
According to the terms of reference of the EIA: "The Project Description
Statement (PDS) commissioned by the developer needs to be audited. This
audit (including sieve analysis and matrix information) should establish
whether the conclusions contained in the PDS are acceptable and whether
the two quarries are the preferred option. The audit should also look
into the assessment of the sites from which the sites were selected.
The more detailed studies of the EIA will be carried out on the preferred
option."
However, the studies presented to NGOs do not contain any such audit
and the option of keeping Maghtab open has also not been considered
in the studies.
From their part the developers, WasteServ and the ministry for resources
are insisting the studies are complete, but correspondence with MEPA
indicates that they are not. Sylvana Debono, MEPA communications officer
told MaltaToday: "the review of the documents submitted by WasteServ
process is still in an early phase and the information will be made
available when the final document is made public. The document will
address all issues mentioned in the TOR."
There remains some confusion about the public consultation period with
some discrepancies between what is being claimed by WasteServ and what
MEPA
has said. However, according to MEPA, which is the body to decide on
the consultation dates, the public consultation period has not commenced.
"The consultation process for an EIA is regulated by law. When
the submissions by the client are made and the report is deemed complete
MEPA will carry out consultations with the relevant Government departments
and agencies as required by law. This process takes a minimum of 30
days
depending on the nature of the report. The report will then be updated
by Wasteserv taking into due consideration the comments by stakeholders
and MEPA.
"The public hearing is likewise regulated by law. Once a date for
the public meeting is set, copies of the final document will be distributed
to the stakeholders.
"The public will then have access to this document through the
offices of MEPA and the local councils concerned.
|
|